Arizona and Pacific RR Current Projects



Arizona & Pacific RR Current Projects

          This page of the website follows projects taking place at the Arizona and Pacific Railroad and gives visitors a chance to see the progress that has been made...




03/08/10

          The waiting area patio behind the engine house was the major project this month. We removed our granite ballast to be used elsewhere later and brought in and compacted several tons of dirt under the patio footprint. Two pallets of concrete later and the pavers are all set in 2 ½ inches of concrete. The patio is a 60 foot by 17 foot rectangle with railroad tracks cut through it.



Waiting Area

The waiting area is starting to take shape





          The pavers are all set and most of them have been cut to shape, but many cuts remain. The number of cuts was almost overwhelming. Then all the cut edges have to be treated. Some of the smaller edge pieces will be affixed with thinset and then the polymer sand will be added throughout.

          Once that phase of the project is completed, I can start on the wood walkway between the rails that will connect the two largest areas of the patio and connect the area with the loading platform and pedestrian walkway. A great deal of time went into the project in the last two months and it still has quite a way to go, but I think you can get the idea of where I am going with this project. Everything except the wood walkway should be completed by the end of March – if it quits raining every weekend….

          We cut and fit another piece of Arizona flagstone to the north side of our engine house this month. This will be the third and final light fixture on that side of the building. The rough wiring is complete. The wiring will be finished and the fixture mounted this month



Wiring for 3rd light

Flagstone installed and wiring in place for a 3rd light fixture on north side of the engine house.





          Just when I thought we were done with lighting projects, we are adding a light switch and receptacle for a railroad drumhead inside on the west end of the building and adding lighting for the attic where we will have some storage.

          We got started on plumbing our G-16 this month. All of the plumbing had been stripped out before we bought her and what we bought was basically a shell with a few parts. Over the years we have tracked down most of the major components. As they always say though, the devil is in the details. We are mocking up the plumbing and cutting, flaring and fitting tubing. Locating and buying fittings, fabricating brackets and slowly moving forward. Dave is tracking down the gauges we’ll need for the instrument panel.

          We made some progress on the S-16 reassemby this month as well, but didn’t have much time to devote to it.

          We are just getting the mainline back together enough to start running the engines and start entertaining guests again. We had visitors from Yardley, PA and Salt lake City, Utah this month. Speaking of travel, I had two more weeks in Las Vegas this month on business. The Hoover Dam Bypass is really starting to take shape.



Hoover Dam Bypass

They continue to make progress on the Hoover Dam Bypass





          I have always thought it would be cool to have a stock car and a caboose to add to our train. I am a big fan of Sean and Melissa at the Hillcrest Shops in California and really like the stock car they produce. Over the years, I had purchased about ½ the metal parts that go into that project and this month purchased pretty much the rest of the metal components that they offer. I will still have to fabricate a few metal components and all the wood, but at least the metal parts will be here. The stock car is a long range project and may be five years away, but I like to plan ahead. The caboose will be after that.

          Happy railroading everybody!




02/06/10

          Sorry about the delayed update, I was out of town all week and just got home yesterday.

          In January, we installed stake pockets on both of our recently built maintenance of way trailers and painted the stake pockets, truss rod washers and nuts and the couplers to match the wood frame. We still need to letter and number the trailers, but that can happen inside this Summer when the heat is punishing on the outdoor projects.



Maintenance of Way Trailer

Stake pockets have been added to the maintenance of way trailers





          We finished our 1961 Allan Herschell Dodgem bumper car project and moved it into the game room. Oak and Walnut pedestals we designed support the rear metal wheels of the bumper car above my Oak floor. The pedestal on which the front wheel sits has a bearing concealed within which allows the top half of the pedestal to spin and thus the front wheel turns when the steering wheel is turned. It’s a little thing, but it is pretty cool to be able to turn the steering wheel. We shortened the pole slightly so that it would fit, but I thought having the pole and the electrical pick-up on the back of car was a nice touch. My brother David found an original sales brochure for the car. It weighs roughly 600 pounds. Five of us (totaling well over 1,000 pounds) struggled to get it out of the shop and into its current spot. It wasn’t pretty, but there she is…



Restored Dodgem

Restored 1961 Allan Herschell Dodgem bumper car





          We finished our 3+ month lighting project and couldn’t be happier with the outcome. We have our five light poles with seven lanterns installed, painted and fully operable. Located at key spots along the right-of-way, they shine enough light to make the occasional after dark operation in the Summer possible without “over lighting“ the area. We selected an older style 60 watt bulb for the lanterns that puts out a yellowish light that adds both light and ambience to the railroad



Light Posts

These two custom built light poles lead the way to the loading platform







Two Armed Light Post

A two armed light post for illuminating the loading platform and it's walkway





          The lantern poles are painted a tan/brown color to simulate the look of wood and structural washers are placed where they would be located on a wood version. The wiring is all concealed within the steel tubes. The outlets are always hot and thus I no longer need to drag out 250 feet of extension cords for some projects. Everything is code compliant with GFI, breakers, wire gauge, connectors etc. The poles and lanterns look good in the daylight, but they are very cool after dark!



Light Posts After Dark

New light posts after dark







Light Posts After Dark

New light posts provide night time illumination





          While we were painting our new lamp posts, we decided to get another coat of paint on our turntable which was completed in 2005. It didn’t really need painted that badly, but had faded a bit over the years and with the new lamp post standing nearby, I thought it was a good idea. We removed all the planking and recoated it with a water and termite resistant product. The ring rail was also painted and everything looks good. The turntable was reassembled over a couple of weeks and should be in great shape for many years to come.



Light Post in Primer

The planking has been removed from the turntable and a nearby light post sports a coat of primer







Turntable Masked for Painting

The turntable is masked for a fresh coat of paint





          About a year ago, we added two high-density seat pads to each of our gons to soften the wood seats a bit. The thought being that the adults might like the padded seats while the younger people probably wouldn’t care if the seat was padded or not. As it turns out, everyone wants a padded seat. We had four more seats made and installed this month in our two gons so now all the seats are padded.



Seat Cushion on Gondola

All the seats on both gondolas are now padded and so are the benches in the engine house





          Last year I designed and built couplers on the rear of our speeders to enable them to tow our maintenance-of-way trailers. When I later changed my mind on the design of the trailers themselves – it meant I had the couplers in the wrong place on the speeders. We had to cut out the original design and fabricate new ones that sit much higher. We also had to move and rewire the tail lights on the speeders. There was a great deal more cutting, grinding, fitting and welding than the last two sentences imply, but the changes are complete and the coupler assemblies have been reinstalled. I still need to sand, prime and paint them,but the balance of the work is done.



Speeder Coupler

Modified speeder coupler





          I also thought our trestle fire bucket/water barrel might look good as our engine house trash can and made that change from the plastic variety.



Fire Bucket

Sedona poses by the fire bucket





          I purchased the additional 3” thick mega pavers we will need for our expanded waiting area and the sidewalk from the waiting area to the boarding area. It took two of us the better part of a day just to get the pavers all moved to their staging area and divided into three piles based on paver size.



Mega Pavers

The mega pavers for expanding the waiting area are stacked and ready







Waiting Area

The current waiting area will soon be expanding and will connect to the loading platform.





          I still need to remove some gravel from the area, bring in and compress some dirt, buy a pallet of concrete and a couple of tons of sand before we are ready to start. I hope to have all the materials on site later this month and get started on this multi-weekend project. There will be a large number of time-consuming saw cuts so this project will take a while…

          I have had three metal benches in the engine house that have provided a place to sit while swapping stories and lies for some time. The metal eventually started to become uncomfortable. I added padding to the seats and back and covered the benches. They are much more comfortable and with some imagination - okay a lot of imagination - look a bit like coach seats from two centuries ago.

          I am still hopeful we can get the expanded waiting area done, the ceiling insulation in the engine house completed and a good start on the T & G ceiling in there before Summer sets in here – we’ll see.




12/30/09

          Last month we started on a lighting project we had contemplated for some time to light enough of the backyard to allow night running. The loading area, the turntable, the water tank area and the switch yard need additional lighting to be able to safely run after dark. Most of our time this month went to continuing our work on different aspects of this project.

          Two of the lantern posts have been completely assembled, welded and wired; only the priming and painting and the installation of the switches, outlets and lantern remains. The other three lantern posts have been cut, drilled and tack welded with the pull wires in place.

          We completed digging the 300 feet of trench under sidewalks and crossing under the tracks several times. We laid the conduit and pulled the wiring. Four of the five concrete mounting pads are complete and the j-bolts and final wiring are in place.



Concrete Slab Hole

Hole and conduit prior to pouring the concrete slab that will secure the lamp posts





          Two of the lantern posts have two arms (at 90 degrees) and three have one arm. Each has an outlet so we will have access to power without dragging 250 feet of extension cords when we are working on projects along the right-of-way



Lantern

One of 7 lanterns that will hang from the 5 lamp posts





          We designed the posts to look the period and struggled with the scale. We have the engine house which is people scale and the engines, water tank and turntable which are 5/12 scale narrow gauge scale. We settled for something close to 5/12, but cheated a little.


Lamp Posts

Two of the lamp posts are roughed in place to check scale





          It is amazing how many hours of shovel and pickaxe work not to mention the hours of cutting, drilling, welding and grinding that get lost in projects like this. Dave, Frankie and I have logged 80 man hours on this project so far and still have a long way to go to have it finished, but we have made substantial progress. It should be finished in February/March.


Frankie

Frankie marks a lamp post for drilling





Lamp Post Pieces

Steel for fabricating the lamp posts





Lamp Post Pieces

More steel for the lamp post construction



          Last month we moved three truckloads of S-16 parts into our Peoria shops to restore and reassemble an engine for one of our friends. This month we gathered several more parts for the project including: the fluid clutch, transmission, gauges and boxes of mounting hardware and misc small parts. All that remains to be moved is the Wisconsin engine which won’t be needed for another couple of months. It is amazing how much less room these things take up when they are assembled…


          We got our new light fixture mounted to the platform side of our engine house. It looks and works great. We have plans to expand our waiting platform in that area.


2nd light fixture

A second light fixture (far right) was added to the North side of the engine house



          I attended two more work days on the F & MV this month. We completed the new spur from the turntable and have 20 feet of a 70 foot privacy fence project completed. We also rebuilt the problem trucks under one of the flat cars and took her around the layout several times without incident.

          Work on our 1961 Dodgem bumper car is nearing completion and it should be out of the crowded shop in January. I am very pleased with the finished product. It looks like it would have when it came out of the Allan Herschell Shops in Buffalo, New York almost fifty years ago. That said, it is so much work and so tedious I don’t think I want to restore another one any time soon… Besides, I need the space for several upcoming railroad projects.

          Happy New Year and safe railroading everybody!




11/28/09

          It has been several weeks since the last update here and as a result, this one may be longer than most.

          I was able to get two vacation days from work on October 8 and 9 and we headed out to California to visit several large-scale railroad sites after work on the evening of Wednesday the 7th. We started our trip with a tour of the historic Hurlbut Shops in Buena Park. Bud and Lonnie have built some of the amusement industry’s classic and most beloved trains over the years. The hospitality and history was amazing and we spent several more hours there than expected as the day flew by.



Hurlbut Shops

Hurbut Shops in Buena Park, California





          Our trip then shifted to Northern California where we visited the Panella Pacific Railroad and friends Bob Smith and Marty Melish, the RS&T Railroad of Rodd and Francille Peters, the MP & BH Railroad of Mike and Lois Davis and the new railroad of Del Osso Farms in Manteca, California. It was great to see the recent developments and projects on each of the railroads.



Panella Pacific Railroad

New loading platform at the Panella Pacific Railroad





RS&T Railroad

New water tank at the RS&T Railroad





MP & BH Railroad

Curved trestle under construction at the MP & BH Railroad





Del Osso Farms

Del Osso Farms Railroad



          We spent all day Saturday at the Reedley Railfest. The Hillcrest and Wahtoke Railroad of Sean and Melissa Bautista is the home of the event which attracts motive power, rolling stock and fans from several hundred miles away. We visited with many of our old friends, made a few more and rode behind some beautiful engines. It was great to see the progress on the many projects Sean and Melissa always have underway. I also had the rare and unexpected privilege of a cab ride in the “Marie E” – very, very cool!



Marie E.

Riding the Marie E.







Railfest 2009

Down in the cut at Railfest 2009 at the Hillcrest & Wahtokee Railroad





          We brought back a wine barrel from Northern California to add ambiance to our engine house loading platform. It looks good out there – thanks Marty.

          We picked up the stake pockets for our two work trailers when we were at Sean and Melissa’s place in California. We don’t yet have the stake pockets in place. We will also need to modify some slats, finish the painting and then add the A & P lettering.

          We added several quad electrical receptacles to our engine house. We have a couple more electrical additions to make in the next few of weeks before we start on the insulation and the ceiling.

          We started on an electrical project we have contemplated for some time to light enough of the backyard to allow night running. The loading area, the turntable, the water tank area and the switch yard need additional lighting to be able to safely run after dark. We have hand dug the 280 feet of trench, laid the conduit and pulled the wires for four legs of the five legs of this project. We still have another leg to trench and pull the wires, concrete pads to pour, j-bolts to place and poles to design and fabricate. We hope to finish this project in the spring of 2010.



Trench

Trenches for wiring to allow night time running on the A&P RR







Trench

Conduit with wiring moving towards the 2nd leg of the project





          We are also adding another light fixture to the platform side of our engine house as we have plans to expand our waiting platform in that area. The fixture is on site, finding the time to install it has been the challenge.

          I attended two work days on the F & MV where we placed the sill beams and completed the rough grading for a new spur from the turntable, placed 6 poles and three posts in concrete to secure privacy fences and diagnosed a nagging derailment problem with one of the flat cars. We will repair the culprit truck on our next work day.

          You may recall from prior updates that we rebuilt the power trucks for an S-16 that one of our friends has been working on for some time. Work on the balance of the S-16 rebuild project has been lagging and we have agreed to complete the project here in Peoria. As a result, we have moved 3 truckloads of parts to the shop at the Arizona and Pacific RR. We will work on the restoration, rebuild and reassembly over the next few months in conjunction with the work on our G-16.



D&RGW S-16

D&RGW S-16 arrives in Peoria





          Work on our 1961 Dodgem bumper car made great advances during the past six weeks. The inside of the fiberglass shell was sprayed with the same coating used for spray-in truck bedliners and does a nice job of covering the fiberglass cloth in the interior. The hardrock maple floor could not be saved and was replaced with a custom reproduction floor also of hardrock maple. The chrome was all dipped, polished and rechromed. We rebuilt the clutch and motor, cleaned, painted and reassembled the bolt onto the floor parts, replaced the belts and cleaned and painted the drive chains.



Dodgem

New hardrock maple Dodgem floor





          The seat has been reupholstered. The steering column has been rebuilt, bearings have been replaced and the steering wheel has been reconditioned.



Dodgem

Steering column and seat bracket on the new hardrock maple Dodgem floor







Dodgem

Repainted Dodgem fiberglass body during chrome installation





          The bumper ring required a significant amount of welding and grinding for both structural and aesthetic reasons and repainting.

          We still have work to complete on the rubber bumper and the power pole, but it is already starting to look like it would have when it came out of the factory. No, it will not be placed back in bumper car duty…

          We did very little actual work on the G-16 this month, but did get some good ideas when we visited the Panella Shops on our CA trip.

          Issue 5 of Large Scale Railroading magazine is taking shape.

          In addition to the 4 ½ days in California and the 2 days in Camp Verde since the last update, I also had 6 business days in Las Vegas and 4 days in Albuquerque. It still seems like we got a lot accomplished under the circumstances.



Hoover Dam Bypass Bridge

Progress on the Hoover Dam bypass bridge continues







Hoover Dam Bypass Bridge

Hoover Dam bypass bridge in November 2009





          Happy Holidays and safe railroading everybody!


10/05/09

          We spent a great deal of our available time this month working on our two Maintenance of Way trailers. The end sills are mortise and tendoned and pinned with an oak dowel. The top slats are White Oak with several coasts of Red Oak stain and attached with countersunk stainless steel screws. The wood work alone was a big job as every surface is beveled or routed. We threaded our own ½ inch diameter cold rolled steel rod for the truss rods. It was fairly standard cutting the right hand threads, but I’m not sure you ever get used to cutting left hand threads for the turnbuckles. We have a couple of good coats of paint on the end sills and frames, but still have some additional painting to finish and some touch up to complete. We also had to enlarge the throat of the couplers to accommodate our tight radius curves. We still have to add the stake pockets, modify some slats for the pockets, finish the painting and then add the A & P lettering. I am pretty pleased with the way they have turned out so far and they roll great!



MOW Trailer

Maintenance of Way Trailer Under Construction







MOW Trailer

Truss Rods, Turnbuckles & Couplers







MOW Trailer

Maintentance of Way Trailer After Installation of Wood







Long MOW Trailer

Long Maintentance of Way Trailer





          I had time to pick up my MTC track gauge this week from my friends Kevin and Xavier at I-17 Collision in Phoenix. They did an awesome job matching the paint and painting the gauge for me. I just finished getting it back together earlier today. It hasn’t looked that good since it left the MTC factory! You can check out the before and during photos in last month’s update.



MTC Track Gauge

Restored MTC Track Gauge





          We are going to be completing some additional work in our engine house this Fall. We are adding six additional electric outlets and an additional set of switches. We are also going to lay approximately 200 additional feet of underground conduit and wire for some future projects we have planned and tie it into a spare breaker in the electrical box in the engine house. We are also going to be insulating the roof and the clerestory walls in the engine house this Winter. The roof will be R38 and the walls in the clerestory section R19. I purchased the insulation and have it stored in one of the other buildings for now. I still need to frame out a few of the areas in the engine house ceiling, but until a few days ago it was still 107 here so I am in no big hurry.



Insulation

Insulation for the engine house





          We did very little on the G-16 this month; we are still trying to locate at least two nice gas tanks. We would really like to locate four and complete our B unit too.

          Issue 4 of Large Scale Railroading magazine will ship from Manhattan, KS on October 9.

          I also started restoration work on a 1960 Dodgem bumper car this month. Yes, I know it isn’t railroad related, but it’s another project out in the shop that competes for my railroad time. It will look very cool when it is completed.

          I had a business trip to Albuquerque, New Mexico this month and due to some last minute schedule changes I had to be there at 7:00 a.m. their time on a Monday morning. As I was traveling on my time on a Sunday, I decided to leave early and check out a few of the interesting places along the route. As many of you know by now, I am a big fan of old Route 66 and many of the old gas stations, motels, diners, theatres etc. that served travelers along that roadway; I am also a fan of railroad depots, steam engines and NAU.

          The first stop was Flagstaff where I had to get a shot of the Lumberjack in front of Granny’s Closet. Granny’s was already established as a restaurant and bar near the Northern Arizona University campus when I attended in the med-seventies. The freight depot (1889), passenger depot (1926) and Southwest Forest Industries steam engine No. 25 which is on display near the freight depot are each interesting stops.



Granny's Closet

Granny's Closet







Flagstaff Freight Depot

Flagstaff Freight Depot







Flagstaff Passenger Depot

Flagstaff Passenger Depot







Steam Enginer #25

Southwest Forest Industries Steam Engine No. 25





          A few miles east of Winona, AZ is the abandoned Twin Arrows Trading Post. It served Route 66 and then I-40 for many years. I remember stopping here when it was still open – maybe 1972ish. A few miles away stood Two Guns - maybe I’ll catch it on another trip.



Twin Arrows Trading Post

Twin Arrows Trading Post







Twin Arrows Trading Post

Twin Arrows





          How cool is the Wigwam Motel in Holbrook, Arizona? There are several wigwam rooms and a larger number of more conventional rooms for overnight accommodation. The parking lot is scattered with period cars and trucks from the 50s and early 60s.



Wigwam Motel

Wigwam Motel in Holbrook, Arizona







Wigwam Motel

Wigwam Motel





          The next stop was in Gallup, New Mexico where I just had swing by the El Rancho Motel. Known locally as the “Home of the Stars”, the motel dates to 1937 and was built by R.E. Griffith, the brother of Hollywood director D.W. Griffith. It was home to several Hollywood Stars when they were filming westerns, primarily in the 50s and 60s, in the beautiful country nearby. They list John Wayne, Kirk Douglas, Errol Flynn, Gregory Peck, Humphrey Bogart and Presidents Eisenhower and Reagan among their guests. The two large signs are pretty amazing after dark, but I was there a bit too early and still had too much ground to cover to hang around until it got dark.



El Rancho Motel

El Rancho Motel in Gallup New Mexico





          I stopped in Grants, New Mexico to top off the gas tank and check the air pressure in a tire. I really like the marquee of the West Theatre (1959).



Movie Theatre Marquee

West Theatre in Grants, New Mexico





          As I entered Albuquerque, I exited I-40 for I-25 and headed south to the Central Avenue exit which is old Route 66 through town. There is a two mile stretch of the old route called Nob Hill which is lined with classic period architecture, retro neon signs, art galleries, interesting restaurants and bars and an old Sinclair gas station that now serves food at tables spread around the old gas pumps. There are dozens of mom and pop “Motor Lodges” along this route, some restored and some not so much. When was the last time you heard the phrase “Motor Lodge”? I stayed at The Hiway House Motel (1959) which was once part of the old Hiway House motel chain owned by Del Webb and which operated my engine No. 1 at its Phoenix location. It was a long day, but well worth it.



Hiway House

Hiway House Albuquerque, New Mexico





          Well, that’s about it from here.

          Happy and safe railroading everybody!


09/07/09

          We finally completed the 16th truck of our truck rebuild project. They are painted, covered and safely in storage awaiting completion of our G-16 and passenger cars. They all have new bearings, seals, brake shoes, hoses, quick connect fittings and plumbing. Most have new wheels and some have new axles. All the brake rigging has been disassembled, straightened, bead blasted, painted and reassembled. Plank bearings were replaced as were broken or badly bent leaf springs. A number of the coil springs were replaced for aesthetic reasons. Each of the 64 vacuum canisters was also rebuilt. Our truck rebuild project was a huge undertaking that has taken several months here on the A & P where we only have Sundays and an occasional Saturday to work on our projects. It does give a sense of accomplishment to have them all reassembled and ready for another fifty years of service when they were bent and mangled junk when I drug that stuff in here, some of it in boxes, years ago!

          Well I thought we were completely finished with our MTC/AH truck rebuilds, but a friend has asked us to rebuild two of his passenger trucks and I have agreed.

          I attended an interesting “work day” on the F & MV this month. When the F & MV has a railroad open house a large turnout is the norm, thankfully, we weren’t having an open house with a lot of guests on this occasion. We went down to the car barn to do some general cleaning and move one of the cars. The intrusion was not well-received by an uninvited guest that had staked claim to the car barn. Wow, you talk about having the crap scared out of you… It took a while to get the rattler out from under the car where we were at a disadvantage. Once it was out in the open, the confrontation didn’t last long, but it was still far from one-sided. Gosh those things are scary and dangerous. This one was an adult and just over four feet long. The fourteen nodes on the rattle indicate it has shed it's skin 14 times. It had eaten within the last day and was slower moving than normal or likely would have gotten at least one of us… Frequently, jackrabbits, quail and gophers are on hand for our work days and an occasional coyote or javalina will make an appearance, but this is the first rattlesnake l have ever seen in 16 years. Malcolm advised it is his second in 40+ years.



Rattlesnake

Uninvited Guest at the F&MV Railroad





Rattlesnake

Western Diamondack Rattlesnake at the F&MV RR





Rattlesnake

14 Bead Rattle





          It was a long, hot month here in Phoenix. The weather will start changing here soon and it will be time to get the trains out and blow the dust off. I had two irrigations in the backyard during the month and had great water pressure both times; the trees and grass flourish with the nutrients from the lake water.

Irrigation

Irrigation at the A&P RR





          We had two commercial picnic tables and two aluminum patio table umbrellas donated to the A & P RR this month and we very much appreciate the generosity. The picnic tables are great for sitting and lunches and the umbrellas provide more shade in an area where I didn’t have much. All will come in very handy as during open houses, there are never enough places to sit. The umbrellas may look retro 1960, but no, they really are 1960 and in very nice shape. I think they go pretty well with all my collection of 1960ish amusement park stuff.

Umbrellas

1960's Table Umbrellas





          We made progress on our two speeder trailers this month. They are a long way from being finished, but are taking shape and you can see what I have in mind. There is still a lot of work to do with truss rods, couplers and stake pockets. The frame needs another coat or two of paint. The planks for the decking are cut, but need sanded, finished, drilled and countersunk for the screws. Then it will have to be lettered. Trailer no. 2 looks about the same as no. 1 at this point – just two feet longer…

Speeder Trailer no. 1

Speeder Trailer Under Construction





          I had hoped to have our MTC track gauge into the shop this month for painting and then have it reassembled. That didn’t happen as I just got too busy with other things. You can see a “before” and “current” shot. Hopefully I will have an “after” shot for you next month. I had to make the rear panel and welded nuts inside the “box” to attach it as the original holes were striped or torn. I also had to make a new axle, find replacement springs and improvise a couple of other missing parts.

MTC Track Gauge

MTC Track Gauge Before Undergoing Restoration





MTC Track Gauge

MTC Track Gauge During Restoration





          We continued with limited time during the month performing sheet metal work on our G-16. We replaced the rear bulkhead which was a butchered up mess. It was easier and cleaner to replace it rather than try and repair all the damage done by prior owners.

          I visited Wickenburg and Kingman this month. Wickenburg has a rich railroad heritage dating back to the old Santa Fe, Prescott and Phoenix Railway and Kingman was on the original A & P (Atlantic and Pacific) Railroad through northern Arizona. Wickenburg has done a very nice job with restoration of the old SFP & P depot and has a static display steam engine and wooden caboose next door. The Kingman depot (1907) is under restoration and the city park has their steam engine on display. Kingman is also on old route 66 and has a number of cool old buildings and period motels.

Wickenburg Depot

Wickenburg Depot





Wickenburg Engine & Caboose

Wickenburg Steam Engine and Wooden Caboose





Kingman Depot

Kingman Depot





Kingman Steam Engine

Kingman Steam Engine





Kingman, Arizona

1909 Brunswick Hotel in Kingman, Arizona on Historic Route 66





          The fourth issue of Large Scale Railroading magazine is at the printer and will mail later this month.

          I had another business trip to Las Vegas this month, the arch of the nearby bypass bridge is complete and the support cables have been removed. Work has started on pouring the vertical concrete pillars upward from the arch to the roadway level. That thing is so doggone high, I am not sure I even want to drive over it… but it looks cool.

Hoover Dam Bypass Bridge

Hoover Dam Bypass Bridge





          Well, that’s about it from here.

          Happy and safe railroading everybody!


07/28/09

          As I shared previously, over the past several months we rebuilt all the journal boxes with new bearings, seals and gaskets, replaced the wheels, replaced worn axles and replaced damaged springs and plank bearings on 12 MTC passenger trucks. Eight of these will go under the rolling stock of our G-16. This month we worked on rebuilding the vacuum canisters, replacing the ¼ tubing and hoses, straightening, stripping, priming and painting brake rigging and replacing all of the brake shoes. Each activity mentioned is more time consuming and in some cases frustrating than you might think. We also devoted time to getting all the brake rigging reassembled.

Vacuum Canister

Vacuum canister ready to be reassembled





Vacuum Canisters

Freshly painted vacuum canisters





          Counting our power trucks and the ones we rebuilt for a friend, we rebuilt 16 trucks and thus 64 sets of brake rigging, 64 vacuum canisters and had to locate and clean 64 sets of rigging pins, spacers, springs and clevis pins. Bolts, washers and multiple sizes of new cotter pins were located or acquired and each set was placed in its own bag until ready to be used.

Brake Assemblies

Some of the brake rigging and vaccum canisters freshly painted in black (S-16) or silver(G-16)





Brake Rigging

More freshly painted brake rigging with the brake shoes still taped





          The four power trucks are completely finished as are three passenger trucks. Two additional passenger trucks are close to completion. Now that the rigging and parts are completed and ready to be reinstalled on the trucks, the pace of reassembly on the remaining trucks will pick up a bit but it is still labor and time intensive getting everything together and set up properly.

          We continue to do body work on our G-16, but spent most of the month working on brake parts.

          We also made some progress on restoring our MTC track gauge this month. We fabricated a rear panel which was missing when we acquired it and bead blasted the “box”. I have a bit more work to complete before it is ready for paint, reassembly and display. I think it will be a very nice piece for our MTC collection.

          I attended another work day on the Flagstaff and Middle Verde Railroad in Camp Verde, Arizona. It rained almost all day, but for a guy who lives in the desert and rarely gets to see rain it was great. I enjoyed the day very much and we still managed to get a few things accomplished.

          I had a handful of out of state guests who enjoyed touring the railroad this month despite the heat. With school vacations and other commitments it isn’t always possible, but from a railroading and personal comfort perspective, the key is to visit in November – April when it is 75 degrees here. We saw 118 on the back patio several times this month which is hot even for us locals…

          I had a business trip to Las Vegas this month and the bypass bridge being built to divert traffic off of Hoover dam is incredible. I know it isn’t railroad related, but is so cool I thought you might enjoy a photo or two I took as I passed through there.

Bypass Bridge

Hoover Dam bypass bridge under construction





Bypass Bridge

Hoover Dam bypass bridge





          Well, that’s about it from here other than the finishing touches are being placed on issue No. 4 of Large Scale Railroading magazine and it will be out about this time next month.

          Happy and safe railroading everybody!




06/30/09

          Our G-16 arrived in Peoria this month as planned. We already have several hours in welding, grinding and sanding with a long way yet to go, but we believe she has a great deal of potential.

G16 in Peoria

Our G-16 Arrives in Peoria





G16 in Peoria

Getting ready for restoration





G16 body work

G-16 body work has begun





          Many years ago, my brother Dave and I purchased two speeders from a downsizing private railroad in the Midwest. Mine has gone through numerous modifications and rebuilds to improve functionality and performance and has been in use here for a number of years. Due to a lack of space here, Dave’s speeder has remained in storage in his garage for all these years. She moved here a week after the G-16; she last ran more than ten years ago.

          What I had envisioned would be a full day project getting her going again turned out to be anything but that. A new throttle cable, some fresh gas and some carburetor fluid and she started on the third pull – unbelievable! She is a great running unit and far superior to my unit even with all the work mine has received.

          We constructed a coupler assembly for Dave’s speeder just like the one on my unit and got it attached. Either speeder will be able to pull either of our trailers

Both Speeders Running

Dave (left) and John (right) take the speeders for a run





          Our G-16 is comprised of the “A” unit, a “B” unit dummy and three passenger coaches. Over the last year or two have we rebuilt all the journal boxes, replaced the wheels, replaced worn axles and replaced damaged springs and plank bearings on 12 passenger trucks. Eight of these will go under the rolling stock of our G-16. Now we are working on rebuilding the vacuum canisters, replacing the ¼ tubing and hoses, straightening, stripping, priming and painting brake rigging and replacing all of the brake shoes. We have phase two completed on two of the eight and are well along on the third one.

Rebuilding a Passenger Truck

Rebuilding a passenger truck





Vacuum Pump

Vacuum pump used to check brake cannisters





          I attended another work day on the Flagstaff and Middle Verde Railroad in Camp Verde, Arizona – it is even starting to get a bit warm up there for railroading – 103 degrees.

          I hosted an enthusiastic group from the St. Vincent De Paul Dental Clinic in Phoenix this month. This group does fantastic things in the community for underprivileged children in need of dental care. Dr. Ken Snyder and several of his dental assistants visited the A & P to gather ideas for a project they have in the works.

Dr. Snyder's Office

Dr. Ken Snyder and Staff visit the A&P RR





          It isn’t all that exciting to read about, but all the equipment here got an oil change, lubricated, fluids checked and a sponge bath…

          Well, there you have it the list of my accomplishments on the Arizona and Pacific since my last update four weekends ago. It was 111 here today and the pace is starting to slow a bit, but we are still plugging away at it.

          Have a great Fourth of July everybody!!!


05/25/09

          We were fortunate in that we were invited to visit the large scale division of the Joshua Tree and Southern Railroad during their meet May 2. The first run of live steam through their magnificent new cut was witnessed and was spectacular. It is amazing what this small group of really dedicated guys is getting accomplished in this one of a kind terrain. If you have never been there you need to visit and check out their progress. Thanks to Ken, Chris, Brendon, Ace and the rest of the crew.

Rock Cut at Joshua Tree & Southern RR

Shay #6 passes through the newly competed rock cut at the Joshua Tree & Southern RR





Joshua Tree & Southern RR

Grand Scale Divison of the Joshua Tree & Southern RR





          I attended work day on the Flagstaff and Middle Verde on May 9. Engines nos. 1 and 2 as well as the track inspection car were placed in service and performed flawlessly. No. 37 (still under restoration – the power trucks are being restored by us) received a great deal of attention and she is quite an eye catcher. I am looking forward to seeing her reassembled and back in service for the first time in many years.

Flagstaff & Middle Verde Power Truck

One of two power trucks being restored for engine No. 37 of the Flagstaff & Middle Verde RR





          I had a several day business trip to Albuquerque, NM with stops in Flagstaff and Winslow, Arizona the week of May 11. I took a photo of the La Posada hotel which has been lovingly restored to its 1929 elegance. Created by Mary Colter for the Harvey House hospitality empire, the design, courtyards, gardens and interior are each very impressive. The hotel is again open and serving guests in what was once called the finest hotel in the Southwest.

La Posada Hotel

La Posada Hotel in Winslow, Arizona





          Old route 66 at one time tied together many of the towns in northern Arizona and stretches of the old route are visible in places between Flagstaff and Winslow. Winslow, Arizona which was once best known as being the headquarters of the Santa Fe Railroad in Arizona was immortalized in 1972 when the Eagles released their first single “Take it Easy”. A statue on the corner, large painted mural and a red flatbed Ford, but alas no girl… commemorate the Jackson Brown/Glenn Frey song.

          “Well, I’m a standing on a corner in Winslow, Arizona and such a fine sight to see its a girl, my lord, in a flatbed Ford slowin down to take a look at me”.

Standing on a corner

Standing on a corner in Winslow, Arizona





Winslow Arizona

It'a a girl my lord in a flat bed Ford...





          We hosted one of our railroad buddies and his family from extreme northern California. It was getting a little warm here, but everyone still had a good time and all the Arizona and Pacific equipment got a workout.

          We just completed the two S-16 powertrucks we were rebuilding for the F & MV Railroad. There is a lot of time and work in totally rebuillding a powertruck - or two. We will get them back in Flagstaff in July and hopefully under the S-16 soon after that.

          Work continues on the restoration on a classic MTC track gauge and a display for our collection of MTC torque wrenches. One of our friends Marty Melish has some ideas for our wrench display which are far better than mine were… I am looking forward to displaying them in the engine house with our other MTC items.

MTC Torque Wrenches

A&P RR collection of MTC torque wrenches





          We replaced the potentiometer on our No. 2 and redesigned the throttle cable assembly hoping to smooth the starts and stops with this engine. This change meant rerouting a lot of previously completed wiring. Our efforts were met with moderate success. Read - it is smoother than it was, but not yet where I would like it to be…

          We are well along in finishing rebuilding a G-16 passenger car truck; one of two needed for the coach that will follow our G-16 around our layout. We have three coaches and a B unit, but will get the G-16 and one coach ready to go first.

          We will be bringing the G-16 and the second speeder to the A & P next weekend from their long-time storage location in Dave’s garage 45 miles away in Gilbert, Arizona. Dave’s garage is about to get much bigger…

G-16 at Dave's House

G-16 at Dave's House






04/25/09

          The last six weeks were a blur with various projects and activities here on the Arizona and Pacific as well as other local railroads. We did manage to get a few things accomplished.

          We got our coupler assembly built and mounted on our speeder No. 1. We still need to get another unit built and mounted on our speeder No. 2. We also made some progress on the two speeder trailers we are building. One is 4 feet long and the other is 6 feet long. We got our couplers welded in place on both ends of both trailers, got them both primed and the shorter of the two is painted. We still need to finish and mount the wood platforms. We also built two draw bars to contact each trailer to a speeder or both to one speeder – depending on what we are doing. Speeder No. 1 will get a “makeover” with new paint and a new windshield later this year.

Speeder Coupler

Speeder Coupler Assembly





Speeder Trailers

Speeder & Trailers





          Our G-16 power trucks are completely finished including the ¼ inch plumbing manifold and vacuum hose. We painted then charcoal grey as our G-16 will sport the traditional warbonnet paint scheme.



G-16 Power Trucks

Both G-16 Power Trucks are Completed





G-16 Power Truck

Close up of G-16 Power Truck



          We are also rebuilding two S-16 power trucks for one of our friends. As many of you know, getting everything apart, cleaned, straightened, primed and painted takes much longer than reassembling everything once it is ready. The abundance of spacers, springs, pins and keys makes the process a tedious one even when you have been through the process many times before. We have one truck near completion and the second is ready to go back together. The S-16 trucks are painted black and will go under a unit that is painted in the old D & RGW “bumble bee” paint scheme and looks pretty cool.

Brake Rigging

Some of the Freshly Cleaned and Painted Brake Rigging for S-16 Power Trucks



          We are still doing some minor sheet metal work on the “Sandusky” as there are a couple of areas I am not 100% comfortable with yet, but she is getting close.

          We rebuilt four additional journal boxes with wheels and axles for future use and will rebuild four more.

          We hosted railroad friends visiting from the mid-west.

          We started restoration on a classic MTC track gauge and a display for our collection of MTC torque wrenches.

          Spring is here which means spraying for weeds and pulling the ones already here - one of the more romantic parts of railroading … smile.

          I attended a workday and two open houses on the Flagstaff and Middle Verde Railroad.

Flagstaff and Middle Verde RR

Open House at the Flagstaff and Middle Verde Railroad



          I finished the 3rd issue of my magazine Large Scale Railroading and got it off to the printer. It will ship in early May.


Large-Scale Railroading Magazine

Click here for more details: Large-Scale Railroading Magazine



          In addition I had business trips to Las Vegas, NV and Los Cruces, NM which ate into my railroad time… Well I think that was about it for the past six weeks, sorry it took so long to get this posted but it has been a bit hectic here. Thank you for checking in on us!


03/08/09

          We managed to get a few things accomplished on the A & P in February.

          We completed work on the set of original style Miniature Train Company block signals that we have been working on for quite a while. Built from parts we have accumulated over the years, they are fully wired and functional, but we will use them as a MTC display in our engine house along with the pair of later style block signals, MTC crossing signal, Allan Herschell crossing signal, non-electrified crossing signal and MTC crossing gate. The gate still needs rebuilt, but it is complete.

Block Signals

Miniature Train Company Block Signals & Allan Herchell Crossing Signal





Signal Display

MTC and Allan Herschell Signal Collection





          We have completed 99% of the body work on the Sandusky cab, our No. 2, and finally have her mounted on the frame. It sure gives her a different look with the cab and the window frames in place. At first glance our No. 1 and No. 2 look exactly alike, however, they were built nine months apart by the Allan Herschell Company and there are a number of subtle and some not so subtle differences.

Cab for the Sandusky

Cab for engine #2, the Sandusky





Sandusky

Sandusky with the cab mounted on the frame





          We have been working on rebuilding our G-16 power trucks for a few months as time has permitted. The trucks each received new wheels, all new bearings and seals, new keys, dogbone boots and new brake shoes. The brake cylinders were each rebuilt and the brake rigging straightened, cleaned and repainted. I still need to build the ¼" copper tubing brake manifolds that operate the vacuum brake cylinders, but that is a project for later in March. The one truck is finished except for the tubing previously mentioned. The second power truck has a couple more weekends of work left before she is completed. Hopefully, both trucks will be 100% complete by the end of March.

Power Truck for the G-16

G-16 Power Truck





          I attended two work days at the Flagstaff and Middle Verde Railroad.

          I am also working on the third issue of Large Scale Railroading which will be distributed in late April. I appreciate your support with that endeavor and your interest in our Arizona and Pacific Railroad projects.

          Have a great March.




02/02/09

          January was a very busy railroad month on the A & P, but there isn’t that much to show really.

          Although they aren’t exactly prototypical, we wanted decoupler levers on each end of our gons. We designed and built the levers which are fully functional. They lift our coupler pin so that the drawbar is released and then the pin slips back into place. They are accessible from both sides of the car. We built four of these assemblies so we would have one on each end of both cars. They all work very well.

Decoupler

Fully functional decoupler lever





          One of our friends does high-end auto interiors on custom street rods. We talked him into making padded seats for our gons. The seats utilize one inch thick high-density foam, zippered cushions and industrial snaps that hold the seats in place. They are removable in case we need to carry a load of coal. Just kidding about the coal part…

Cushion

Custom fit cushions for the gondola seats





          We also worked on another set of Miniature Train Company block signals we are building from parts we have accumulated over the years. We still have a ways to go to have them together and functional, but got a very good start during the month.

          I have most of the body work on the Sandusky cab complete and hope to have it finished and mounted in the next couple of weeks if I can just find the time.

          I attended two work days at the Flagstaff and Middle Verde Railroad and the Third Annual Operations Meet of the Maricopa Live Steamers at Adobe Mountain Park.

          I also managed to get the second issue of Large Scale Railroading completed, printed and distributed. I really appreciate the grass roots support the magazine is receiving. The third issue is in progress at this time.




12/26/08

          The Saturday and Sunday after Thanksgiving was a track work weekend. There were four of us on Saturday and five on Sunday. It was a long, hard weekend, but we did get a lot accomplished. We cut several pieces of rail and increased the space between rail ends to better allow for expansion in the summer, dug out and replaced several ties, replaced the original lag screws in areas near the front lawn with galvanized lag screws and re-ballasted and re-leveled some areas. We still have several more ties that will get galvanized screws after the first of the year, but our track in general should be in great shape for several months.

          In our last update we shared we had our new arch bar trucks under our two new gons. Prior to positioning them behind No. 1 and No. 2, we pushed them around the entire layout in both directions to make sure the trucks were happy and that we had plenty of clearance with switch stands. The cars are 10 inches wider than the standard S-16 cars and I had calculated that before ordering them, but a slow speed field test is always a good idea anyway. They fit and roll beautifully.

Gondola

Gondola 218 waits at the loading platform





          The custom couplers we made for the back of the S-16 tenders are about an inch higher than the couplers on the new gons, so the “link” we had intended to use wouldn’t work. So we made a custom drawbar to connect the two. It looked great, but the small radius of our curves created a serious binding problem on our first pass through our tightest curve. The gon was pushed back into the engine house. We took a second pass at designing a draw bar and modified the gon couplers by widening the throat significantly. We also built about an inch of “slack” into the draw bar to make the ride a bit more realistic. We will see if we like that effect long-term, but we have it for now.

          No. 1 pulled from the engine house with gon No. 218 in the rear for that gon’s maiden-powered trip around the layout on December 13th and performed very well. It wasn’t long before several passengers from the neighborhood and friends from San Diego were aboard. After we knew the changes were a success, we made the same parts for and changes to gon No. 219.

Gondola

Passengers take Gondola 218 for a test ride





          We also added brake wheels to the gons for effect. One of the assemblies we purchased from Sean and Melissa at Hillcrest Shops and the other we fabricated here. We did modify the first one significantly and added spring tension and a clicking ratcheting effect to both assemblies. I thought it would be a nice effect for the kids, but every adult that walks past seems to “have” to turn the brake wheel and listen to the ratcheting sound. They are not actually hooked to the brakes, but they do give that effect.

Brakewheel

Custom brake wheel added to gondola





          For years I have had a MTC crossing signal, Allan Herschell crossing signal, MTC two light block (mid 50s style), MTC three light block (mid 50s style)and MTC Non Electric crossing signal stored in the back of my garage. Several years ago, Dave and I took them all completely apart and cleaned and repainted everything. We replaced broken lenses, repainted all the signs, lubricated the bells etc. Then because I didn’t have a place to put them, they went back into storage. We just custom built some heavy raised plates to mount them to so that I can display them in the engine house without fear that they will topple over (they are very top heavy) on anyone. I also have a mid 50s MTC crossing gate that I may rebuilt one day – we’ll see. After being in and out of storage and then being moved, the crossing signals and blocks have accumulated a few nicks and scratches that need touched up but at least now they are out where people can enjoy them. In time, we will have a control box out there that will allow people to activate the signals. If the bells get too annoying those wires may come loose – smile…

Signals

MTC and Allen Herschell signals on display





          We finished work on the stanchions on engine No. 2 last week. What a time consuming project that was getting them set just right and grinding the heads on new bolts in the steam dome to allow the boiler assembly to slide smoothly! We have just barely started on the cab sheet metal for No. 2, but hopefully will have the cab on the Sandusky in the next month or so and she’ll look a bit more like an engine.



Sandusky at Christmas

Sandusky poses for a Christmas photo





          All in all it has been a very busy five weeks. Thank you for checking in and seeing what we are up to out here on the Arizona and Pacific Railroad. Have a great New Year everybody!

Christmas at the A&P RR

Merry Christmas from the Arizona and Pacific Railroad






11/23/08

          The first week the new gons were here in Peoria, they spent on blocks and under tarps in the driveway. The following weekend we placed temporary trucks under them and got them moved into the engine house where they were again placed on blocks while we worked to complete the arch bar trucks.

Arch Bar Trucks

Arch Bar Trucks





          The first set of trucks were completed and painted the weekend of Nov. 8. Late that Sunday afternoon, we got them under gon No. 219 and she made her first appearance on the A & P. There were a couple of locations where we were concerned that the clearance might be somewhat tight, but everything was just fine.

Gondola #219

Gondola #219 on the transfer table





          The second set of trucks was finished the next weekend and that Sunday we got those trucks under No. 218. We had the transfer table, turntable and several switches all in use as we repositioned No. 218 behind locomotive No. 1 in stall 1 in the engine house. No. 219 was moved in behind locomotive No. 2 in stall two of the engine house. Stall three is currently storing our pump car and will soon house the two speeders as well.

Gondola #219 with passengers

Three passengers tryout Gondola #219





          We are in the process of fabricating couplers for the rear of the two S-16 tenders and moving some wiring and connectors to make room for a stiffener panel on the inside of the tender frame. If all goes well, that will occur over the long weekend with Thanksgiving. We purchased a brake wheel assembly from Hillcrest to see if we would like the look of a brake wheel and shaft on our gons even though we will not have it connected to brakes. It looks good so we bought a second wheel from Sean and Melissa and are fabricating our own mounting hardware on the second one. We should have both of those mounted next weekend too.

          We finished the speaker wiring and installation on No. 2 this week and they work fine and sound good. We still have some work to complete on the handrails and then I need to get after the cab sheet metal and get that finished. The four remaining window frames have already been bead blasted and are in very nice shape.

Instrument panel on Sandusky

The instrument panel on engine #2, Sandusky





          We finished rebuilding (new seals, bearings and wheels) three more Allan Herschell trucks this weekend. The frames were bead blasted, primed and repainted. They still need new plumbing, brake shoes, and vacuum canister rebuilds as well as rigging adjustments, but we have a good start on the process and they really want to roll!

          The Saturday and Sunday after Thanksgiving will be a track work weekend with some rail being cut to allow better expansion in the summer, replacement of several ties, replacement of lag screws in areas near the lawn with galvanized lag screws and reballasting and leveling in areas. After those projects are complete we should be good to go for the next few months on our track work.

          Happy Thanksgiving Everybody!


10/31/08

          Several months ago, I contracted with Sean and Melissa Bautista at Hillcrest shops in Reedley, California to build us two gondola cars. They are always busy building or restoring cars and engines, laying rail on their railroad or someone else’s and working on various construction projects around their railroad – not to mention their real jobs. There is always a waiting list for their equipment, but it never disappoints. Our cars were completed the end of September and we loaned them to the Hillcrest and Wahtoke Railroad for use at their Reedley Railfest held the weekend of October 11 and 12. They made their public debut on a train lead by the beautiful engine named the “Sonoma” at the popular and well attended festival.

Sonoma

Sonoma running at the Hillcrest and Wahtoke Railroad



Hillcrest Gondolas

Moving the A&P RR gondolas with a Hillcrest Davenport engine



Hillcrest Gondolas

Removing the 15" trucks used for Reedley Railfest from the new A&P RR gondolas





          I headed off to northern California bright and early at 5 a.m. (okay not bright, but it was early) on the morning of October 25 with a 22 foot trailer in tow to retrieve our two gons at Hillcrest in Reedley and to pick up a “project” B unit for our G-16 from our friends at the Panella Pacific Railroad just south of Lodi, CA. Prior to this trip, I thought the interstate highways in Arizona were in need of some resurfacing and repair work - and they are… Even traveling at only 55mph through southern California, I think I may have rattled loose a couple of teeth fillings… Unbelievable roads!

Loading the Hillcrest Gondolas

Loading the new gondolas onto the trailer for the 16 hour drive to Peoria





Loading the Hillcrest Gondolas

Loading the B unit at the Panella Pacific Railroad





          We did get some thumbs-up on the way back from other motorists and props from a really cute gal at a gas pump outside Newberry Springs, California who knew the B unit was a Miniature Train Company product. How unbelievable is that? No, not that she was really cute and speaking with me, but that she knew the sheet metal was MTC when most of my railroad friends wouldn’t even have known that… I was so surprised and stunned, that before I could even ask how she knew it was MTC equipment she and her friend were back in their truck and driving off…

Trailer heading to Peoria

Loaded trailer heading for the Arizona & Pacific Railroad in Peoria





          Anyway, after 16 hours of windshield time Saturday followed by 16 more on Sunday, the gondolas and the B unit were unloaded here in Peoria. Years ago, traveling 1600 miles and 32 hours in two days was an adventure and fun – maybe not so much in my fifties… It feels good to be home.

          I planned to have the arch bar trucks that will go under these gons completed by now, but still have some final details and paint to complete. I will get after that in the next couple of weeks. We should have the gons on the rail and operating here by Thanksgiving – at least that’s the plan. The B unit will go into storage for now.

          On another topic, we finished wiring the instrument panel on our S-16 No. 2 the “Sandusky”. The switches for the headlight, dash lights and tender back up light were installed. The sockets were wired and everything was tested and works fine. We are currently working on the sound system.




10/08/08

          It has been a while since I updated the projects page so I figured you deserved an explanation of what I have been up to the last several weeks. I started a magazine entitled Large-Scale Railroading which in many ways is a celebration of rideable scale railroads. If you think you might have an interest in subscribing, check out the link to that website (click on photo below). The inaugural issue ships the week of October 13. It isn’t a big publishing conglomerate, just me with some help from some friends, but I’m happy with the first issue and hope it will get bigger and better as we go along. The first issue is 56 pages. If you like my writing style and sense of humor here, you will probably enjoy the magazine.




Large-Scale Railroading Magazine

Click to visit Large-Scale Railroading Magazine


          I am in the midst of rebuilding 10 Allan Herschell coach trucks, two power trucks and designing and building four arch-bar trucks utilizing Allan Herschell wheels and axles. These AH and MTC trucks were all purchased very used many years ago from a variety of sources and have been stored all this time and I am finally getting to them. The trucks were completely disassembled and bead blasted. The leaf springs were checked for condition and alignment and the plank bearings were checked for wear. Wheels and axles were replaced as needed. The bearings and races were all cleaned and checked for wear. About 60% of the bearings and races were still in great shape and just needed cleaned and fresh grease; the balance were retired. All the seals were replaced. The wheels and axle assemblies and the frames were painted separately and then touched up after assembly.

Trucks

Coach trucks in phase one of their rebuild



          Phase two of the AH coach truck rebuild process will start in November when I start to clean, straighten, paint and hang brake rigging. I also will be building 12 brake line manifolds as the originals were too mangled to be reused. Then it is on to brake shoes and vacuum canisters… - no, there won’t be “film at eleven”, but I will keep plugging away.

Trucks

Four coach trucks being rebuilt



          The two power trucks are apart and the journal boxes have been rebuilt. The bearings and seals for the gear boxes are now on site and I hope to have these power trucks done early in 09 as time permits.

Power Trucks

Power trucks, bearings and seals for rebuild



          I am also about half way along in building two small (4 foot long and 6 foot long) MOW flat cars that can be used to haul tools and other materials back and forth to assist in maintenance and new construction. The MOW cars also utilize Herschell wheels and axles, but not its trucks.

          There are three major reasons why I have tried to build as much of our rolling stock as possible out of MTC/ Hershell wheels and axles. One, it is technology proven over time. Two, the bearings, seals, axles, wheels and other components are the same on most of our equipment thus I know the parts are available and the parts shelf doesn’t have hundreds of different parts. Okay, it does have hundreds of different parts, but not thousands… Three, mixing and matching multiple wheels and flanges can make for an interesting afternoon.

          The Arizona and Pacific Railroad utilizes cast frogs of the Miniature Train Company or Allen Herschell variety on all but one of its switches. The frogs are exceptionally smooth when MTC and AH wheels or wheels which follow those wheel and flange profiles are used. Wider and deeper flanges as well as taller wheels make for a rough ride through the frogs and frequently the ride gets even rougher through the gravel… The real “fun” starts getting the wheels back on the rails.

MTC Cast Frog

Miniature Train Company Cast Frog



          Progress continues on the “Sandusky”. The plumbing for the gauges is complete, some additional wiring is finished and a number of “odds and ends” have been finalized. The headlight sealed beam and retaining ring have been installed. You would think that would be an easy task – well not so much. The headlight pocket was originally designed for a 6 volt sealed beam in a style which was slightly thinner. Problems arose when the retaining ring grove was not accessible with the new 12 volt sealed beam in the pocket. Lots of adjustments, modifications and hours later, the headlight and retaining ring are in place and look pretty good. The “to do” list on No. 2 is getting shorter.

          Our four arch bar trucks which also utilize AH/MTC wheels and axles are finally nearing completion. They will go under our two gondolas built by Hillcrest shops. The cars will get their “christening” the weekend of October 11 and 12 at the Reedley Railfest held at the Hillcrest Shops in California. They were a couple of cars short for their festival so we volunteered our cars which will be rolling on their trucks for the weekend. We plan to have the cars here by the end of the month, so I better quit typing and get going and get some more work done on the trucks. Have a great weekend everybody.




8/23/08

          We just completed editing last week's video footage taken by remote controlled airplane. You can check out the finished video by clicking here: Arizona and Pacific Video Page. It's the second video on the page. We also managed to get a few screen captures that are shown below.




A&P Aerial Veiw

Screen capture from the video



Turntable

Nice view of the turntable

Loading Platform

The loading platform is visible in this screen capture



Phoenix

Phoenix sits on trestle #5

Engine House and New Siding

The engine house and new siding







8/16/08

          A friend of Dave's named Jerry Carter brought his remote control airplane to the A&P Railroad today. Jerry's RC plane has a video camera attached and he shot a few minutes of video as he flew over the Arizona and Pacific Railroad. After we get the video and have a chance to edit it we'll post it on this site.



Lil Banchee 3d

"Lil Banchee 3D" Airplane




Preparing for takeoff

Preparing to take off




Flyover

A&P RR Flyover






          We've been making good progress on the Sandusky. The brass boiler bands, custom made stanchions and handrails have been installed since the last time she was photographed. The headlight has been wired and we're working on the plumbing for the vacuum gauges on the instrument panel.

Sandusky

Sandusky







7/12/08

          Two weeks ago, we finished the bending and gauging on the final section of rail in our new spur. The spur is 120 feet long. The final ballast work remains to be completed, but the rail and tie work is finally done. We also have a couple of minor adjustments to make on our new switch and that will happen later this month.

          Well, the temperature plummeted to 110°F last weekend so Dave and I seized the opportunity to do some track work. We dug out twenty-five of the ties we originally set in 1995 and replaced them with new ties. The problem here isn’t water causing the ties to deteriorate, it is the dryness and the heat. The ties check, splinter and crack after several years cooking in the hot gravel ballast.



Tie Maintenance

ROW maintenance taking place (left) and new spur (right)






          I had ten more tons of that hot gravel delivered yesterday to finish the new spur and refresh some other areas where track work has created a need for additional ballast. To assist in moving the gravel from the front street to the rear yard where it is needed, the smallest of the Flagstaff and Middle Verde Railroad ballast cars is visiting the A & P this week. Constructed nearly twenty years ago, it last saw service on the F & MV several years ago. She will see 10 tons of activity down here this weekend.



Ballast Car

10 tons of ballast




Ballast Car

F&MV RR small ballast car visiting the A&P RR



          We are still plugging along and trying to get the miserable jobs completed this summer so that we can play the rest of the year. Labor Day to Memorial Day is the best weather and most fun time of year here, pretty much the opposite of most of the rest of the country. We already have June behind us – just half of July and August to go!



          Last year, we contracted with Sean and Melissa Batista of Hillcrest Shops in Reedley, CA to build us two gondolas to pull behind our S-16 engines. Their craftsmanship is always in great demand and thus they have a waiting list for their cars, but their work is always well worth the wait. Melissa recently sent me some progress photos which show the cars under construction in their shop. Only the sides, seats and lettering remain to be completed. We will utilize our own trucks. We plan to have the gons in use on the Arizona and Pacific this Fall.



Hillcrest Gondolas

Hillcrest gondola construction photo



          Rebuild and reassembly on our G-16 power trucks will have to wait a month or two as I don’t want to waste the opportunity to complete our track work in this cool weather – smile! Here is a photo of the track gang. Dave is on the left and I am on the right. That “but it’s a dry heat” thing isn’t what it is cracked up to be…



Track Crew

Photogenic track crew




6/22/08

          Well, summer has definitely arrived on the Arizona and Pacific. Saturday the 21st was the first full day of summer and the thermometer in the shade on the back patio read 118°F at 4:30 and climbed to 119°F before heading back down. This is the desert and it is supposed to be hot this time of year, but anything over 110°F and it is tough to stay motivated to get much accomplished out there. The heat pulls the water and energy right out of you.



118 in the Shade

First day of Summer






          Despite my whining, we have made some progress on our new switch since the last update. It still needs some adjustments, but the switch stand has been installed and the switch is functional. We continue bending rail on the siding we are constructing and a few feet of additional rail has been tied down. The ties have been spaced and some ballasting has been completed.



Switch on Trestle #1

Switch on trestle #1






          We hosted some railroad friends from Flagstaff, Arizona early last weekend and everyone had a good time. The pump car, speeder and No. 1 all performed well. By the time we started to get No. 2 out of the engine house, it was just too hot to be much fun and we decided to leave her in there. That will be the last of the “tours” until the end of September when the weather becomes a bit more accommodating.

          The frames of our G-16 power trucks returned from the bead blaster last week. Rebuild and reassembly will begin next month.





6/7/08

          Fitting and mounting the various brass components to engine No. 2 continues. We made three custom brass bands for the boiler and are still adjusting our custom made stanchions and handrails. We have quite a way to go, but are continuing to make progress.

          We completed the last of the wood planking on our pedestrian walkway which allows guests to walk comfortably and safely across the three sets of tracks on their way to reaching our primary loading area. The 16 foot long by 33 inch wide loading platform was finished and discussed in a previous update.



Pedestrian Walkway

Pedestrian walkway to the loading platform






          We have resumed work on an additional siding which will allow us to enter and exit the engine house without using the turntable. This siding involves rebuilding the trestle over Rock Creek once again; this will be the fourth incarnation of our trestle at this location in 12 years. We are widening it to facilitate a switch to the new siding. We are also building the new switch that will sit on the expanded trestle. We have patterned it after our existing MTC/Allan Herschel switches. The switch stand will be located just south of the trestle and the points and frog are on the trestle itself.



Switch

Building a switch on trestle #1






          We did quite a bit of digging to level the ties of the partially completed siding with the mainline and added several additional ties. A great deal of work remains on the siding especially with rail bending, but we hope to have the switch portion completed and operational this month.



Track Work

Digging down to level the new siding






          The rail bending is a slow, tedious and physical process for us. Friends of ours in California initially rolled eight pieces of rail that got us started with our curves years ago. They had a beautiful homemade bender that utilized a Wisconsin engine, hydraulic pump and rollers that matched the profile of the 12 pound rail exactly. They set the adjustment on the bender and the powered rollers pulled the rail back and forth curving it to the desired radius.

          Our regular process is a bit different. We use an old fashioned “Armstrong” bender. We set the bender in place, crank the shaft three 90 degree turns, loosen it and move the bender six inches. We repeat this process until we reach the end of the rail and then reverse direction and work our way back to the other end of the rail. It may take several passes until we get the smooth radius curve that we desire. We actually have a hydraulic version of our manual bender and it is a great deal less work, but we just don’t get the same “baby-bottom smooth” curves with it and thus it rarely gets used. Our “old school process” may be one reason we cringe when a NEWBY asks “where did you buy those curved track panels that you bolted together for your curves?”



Rail Bender

"Armstrong" rail bender






          We also started on a longer range project and disassembled the power trucks of our G16 last week. The worm gears look great and I was very pleased with that turn of events. We will replace the bearings and seals and add brand new wheels. The axles are fine. The vacuum cylinders will be rebuilt and new brake shoes will be added as part of the process. The copper vacuum manifolds are a mess and we will build two more as replacements. The truck frames will go the bead blaster this week. Our G16 won’t be placed back in service until next year, but having another project that I can work with inside when it is 116 degrees outside is always nice. Happy Father’s Day!




5/24/08

          We're making progress at the Arizona and Pacific Railroad despite the crazy weather. Last Sunday it was 109°F while we were working on the walkway to the loading platform. Dave's job had him in Dallas on Thursday and when he returned it was 55°F and there was an inch of rain at his house (~15% of our annual rainfall). Weather permitting we'll have an update soon.


          I didn't get any photos at the A & P RR last weekend but I did visit the Forest Park Miniature Railroad in Fort Worth while I was in Texas this week. You can read the spotlight article of my trip here: Forest Park Miniature Railroad



Forest Park

Engine #105 at the Forest Park Miniature Railroad






5/10/08

          We shot some video of the Arizona and Pacific that you can see by clicking here: Arizona and Pacific Video Page



Phoenix

Engine #1 Phoenix poses on Trestle #5






5/05/08

          We have been working on several projects in the four weeks since the last update. We finally got the telephone, clock and thermometer mounted in the engine house. The stereo and TV shelf is mounted in the corner so I can work on trains and have something to listen to in the back ground. We also got the A & P RR train schedule board up on the wall. We bought a new craftsman toolbox and moved many of the tools used exclusively on the trains from the garage into the new box in the engine house. We also mounted our grand scales railroad builders plate display in the new engine house. We have several original and a couple reproduction builders plates from past and present manufacturers of 15 – 24 inch gauge park locomotives on display. Among our favorites are an original Sandley and Cagney and a reproduction Chance plate. We have plenty of room for more and are always looking to add to the collection…

South Wall of Engine House

We've Begun to Utilize the Inside of the Engine House



Builder's Plates

Display Showing Our Collection of Builder's Plates





          We have started fitting and mounting the various brass components to engine No. 2. We still have quite a way to go, but have made noticeable progress. We are continuing to fine tune her operation with brake adjustments, wiring dash gauges etc. Nos. 1 and 2 both make their home in the new engine house now.



Numbers 1 and 2 in the Engine House

Engines Number One and Two Inside The Engine House





          We extended our pedestrian walkway and constructed a 16 foot long by 33 inch wide loading platform which makes it easier to get in and out of our cars. We still have a bit of unfinished work to complete to finish the wood planking where the pedestrian walkway crosses the first set of tracks. A covered (read shaded) waiting area will be to the east of the pedestrian crossing. We haven’t quite finished our two maintenance of way flatbed cars, but one was thrust into service with a make shift piece of plywood as decking on our loading platform project. We have resumed work on an additional siding which will allow us to enter and exit the engine house without using the turntable.

Loading Platform

The Loading Platform is Nearing Completion



Maintenance Car

Maintenance of Way Car Pressed Into Early Service





          We also had an open house and had railroad guests on two other weekends during the month and during the “off Saturday” the Arizona and Pacific Railroad and its structures served as the backdrop for wedding photos (no not Dave or I); who says people don’t dress to ride the railroad anymore… Coming soon, Dave is working on a video of A & P No. 1 in action. Happy Mother’s Day!




4/05/08

          We made some progress on the engine house in the last week. The logo signs on the building have been completed and installed. The pedestal for our harp switch stand has been completed and the switchstand is in place – forgot how heavy that thing is. The four interior fire extinquishers have been mounted. Although a great deal of door hardware awaits mounting, the dead bolts are finally in place and the doors can be locked. The main logo sign has been completed and mounted in its frame; we still need to paint and mount the lower sway bracket. Now the engine house focus can shift to the interior and we will get started on the balance of the finish work.

Harp Switch Stand

Harp switchstand on completed pedestal & painted logo sign installed





Engine House Interior

Now we can focus on the interior of the engine house





A&P Logo

A&P main logo sign painted and mounted in it's frame





Sign in Progress

Laser cut letters & rings are welded to both sides of this A&P logo sign








3/29/08

          There are still lots of things to do on the interior of the engine house from finish carpentry to mounting fire extinguishers, but we finally put the finishing touches on the stone work this week. Did I mention how excited I am that we are done cutting and fitting stone? We also finished the final coat of paint on the doors, door jambs, arch panels and the hand railing. The doors are back up and we have a good start on getting the balance of the hardware installed. We have already run the wiring to tie the security system in the engine house into the one already in place in the superintendent’s house. After the door hardware is all in place in the next week or so, we can get the sensors hooked up and won’t be too far from moving our equipment into its new home.

          We still have a bit of finish work on the exterior to complete with the two logo signs that have to come down and have some finish grinding and the rings and letters welded in place. Plenty of seam sealer, a few good coats of paint and a nice layer of clear coat later and they will be ready to reinstall. We also have a stone pedestal which needs finished to display our harp switch stand.

Engine House

Enginehouse with painted doors and completed stone work





          As our engine house project is beginning to wind down, we have started on another significant project in the reassembly and conversion to battery power of our second S-16. Our first S-16 (No. 1) runs great with its Wisconsin engine and has plenty of power for all our needs, but even with its muffled exhaust it is a bit loud for our “urban railroad”. We have neighbors on each side who are somewhat less enthusiastic about railroads and railroading than we are – I know hard to believe!

          We rebuilt the original power trucks and drive lines of our No. 2 with all the standard parts. The engine, transmission and fluid clutch were replaced with a 48 volt electric motor and drive assembly designed by Brian Stepaniak of Scaled Plus in Ontario Canada. The battery tray and all components were designed to fit into the original brackets and mountings holes on the S-16. It is a very clean and professional conversion. We have her assembled and have made several break-in runs with her. We still have a couple of minor bugs to work out with a faulty DC converter and a problem draw bar, but we have more power and top end than with our Wisconsin, no leaks, no exhaust and no noise. We also have a parking brake in addition to the factory original vacuum brakes – all things other G-16 and S-16 owners can appreciate. We haven’t run enough yet to have a good feel on the actual run time versus calculated run time, but the calculations indicate 8-10 hours of run time with three fully loaded cars per charge.

The Sandusky

Brian Stepaniak takes The Sandusky for one of her intitial runs





          It appears to be a great solution to many of the challenges faced by G-16 and S-16 owners as their unit’s age and engine, transmission and clutch parts become more scarce and expensive. It also helps private owners and park railroads effectively deal with neighbors concerned about noise and pollution. The only problem so far – it may be too quiet…

          Anyone interested in contacting Brian can access his website at www.scaledplus.com or call him at 705-663-1546. Tell him you heard about him here.




2/15/08

          Last week, I stated I would try to get a few photos of our progress on the rock work posted. Well, as promised, here are a few photos of the rock work on the west and the south sides of the enginehouse. The columns, arches above the doors and the trim around our logo took seemingly forever, but add some detail and character to the west face. The two large gooseneck light fixtures also contribute to the look and put out a great deal of light. The soldier course window sills, the window trim and the length of the building were the main challenges on the south side. We have the two toughest sides done and have started on both the east and north sides of the building. We are probably about sixty percent finished with the rock work overall. We wanted a really distinctive rock look for the enginehouse and we definitely have achieved that, but to quote a line out of one of the old Rocky movies, “Ain’t gonna be no rematch” - read no more stone buildings for me after this one is finished.

Rock Work

Rock Work on the West and South Sides of the Engine House






2/09/08

          Significant progress was made on our enginehouse project in January. Our second electrical inspection planned for the last week of December was delayed by the holidays. That inspection as well as our “Service Section” inspection and “Final” took place the first two weeks of January and went very smoothly. The electrical is complete and it sure is nice having service out there without dragging 200 feet of extension cords!

          The next project we tackled was an epoxy floor finish for the enginehouse. As most train owners will tell you, each engine has her own personality, idiosyncracies and leaks. There is a practical limit to eliminating every leak so I wanted to coat the floor such that cleaning up afterward is as easy as possible. We met with several vendors and made our material, color and contractor selection. We were initially told it would take four days to complete the floor. Well a cold front hit us the same day they started on the floor. This is the desert and can get much colder than many people realize. We had night time temperatures in the low and mid twenties several days in a row with highs in the low fifties. This meant instead of applying a coat of material first thing in the morning and another late in the day after the earlier coat had cured, only one coat per day could be applied. It took eight days to complete the floor, but was worth the wait. It looks good, has texture to keep it from getting slippery and best of all oil, hydraulic fluid etc. wipes right off.

Engine House Epoxy Floor Finish

Epoxy Finish on the Engine House Floor





Engine House Epoxy Floor Finish

A&P Engine House Floor





          Our current focus is applying one inch stone veneer to the outside of the enginehouse. We wanted a look reminiscent of some of the old stone railroad buildings in Colorado and throughout the West. The product we selected is a real stone product quarried north of Prescott, Arizona and distributed by 3North Stone. We started on the most labor intensive side, the west face, first. The columns, arches, corners and border around the round logo required hundreds and hundreds of cuts and made for very slow going. Trust me, you don’t want to know how many hours we put into that first wall. We are currently working on the south wall and the pace has picked up due to less cutting and our familiarity with the product and process, but you still don’t want to know… We hope to have all the rock work finished this month – February. I’ll try to get some photos of the rock work taken and added soon.

          After we finish the rock work, we will paint the doors and door frames, install the door hardware, sweeps, stops etc. and get the security system installed.


12/25/07

          My computer contracted a virus shortly after our last update. After nearly a month in and out of the shop without much meaningful repair success, she was retired and replaced. Our updates should be back on track soon and the annual report should be available the first week of January as usual. Thank you for your interest and patience!

          We had a great deal more success in the last month with the engine house project than the PC… The exterior painting is complete except for the doors and door frames. The door hardware is all on site and will be reinstalled after the doors are painted. The exhaust fans and ductwork have been installed and only await the electrical. We went with two 429 CFM fans and eight inch ductwork. We have the four sets of double doors, the single door, 80 feet of vents in the soffits and the two large round vents upstairs. The mechanical people who calculate these things tell me that the two fans will be plenty; we’ll see and can install two additional exhaust fans if necessary.

A&P Engine House

Clerestory and Trim Paint Completed





          The steps and handrail to the main door are in place. The handrail still needs painted and the sidewalk is under construction. The pad and sidewalk on the north side of the building have been completed.

Front Steps

The front steps are complete and the sidewalk is in progress





North Sidewalk

The north sidewalk and pad have been completed





          Phase one of the building and its permit are complete and we passed our final inspection on that permit on December 11. Our permit for Phase 2 was pulled on December 13. This phase is the electrical. It includes the installation of a 100 amp subpanel, interior and exterior lights, numerous receptacles and the exhaust fans. It also requires upgrading and replacing the main panel on my house and 225 feet of trenching 20 inches below the grade to connect the two panels. Three inspections will be required. We have passed the first inspection, the second is scheduled for December 28 and the final will be sometime after the first of the year.

Electrical Subpanel

100 Amp electrical subpanel to service the engine house





          Phase three of the engine house construction project is primarily aesthetic and includes rock on much of the exterior, door veneers, insulation and some T111 paneling in the clerestory area and some interior painting , installation of the alarm system and some finish work. It will be late Spring before all these items are finished, but we will keep plugging away at it

Rock Facia

The cases of rock facia have arrived on site





Doors

The doors have been hung and painted with primer





          Happy New Year Everybody!




11/19/07

          We have a bit more progress to report. The soffits have been enclosed and the soffit vents have been installed. The round vents at each end of the clerestory roof have been added and the wood siding on that portion of the building is now complete. The steps and hand rail to the main entry door are nearing completion. The mockup of the A & P logo has been added to the end of the building. The final version is very colorful and three dimensional instead of the mockup’s painted letters and ring.

A&P Engine House

The Wood Siding is Completed






11/13/07

          Progress on the enginehouse continues. The shingles are in place and are a special dimensional shingle designed to look like wood shake shingles. The effect is much better from some angles than others, but they look pretty good all in all. The upper and lower windows have been installed and the flashing membrane has been installed around the upper windows. You will also notice that we have started on the steps up to the main entry. We are really pushing, as time and money permit, to try and finish the building before the end of the year, but it is starting to look like January before we can get it finished. We’ll see how far we can get.

Engine House

The Roof Has Been Shingled






10/31/07

          We have had a busy several days at the A & P working on the engine house. The roof is on and awaiting paper and shingles, the framing is finished and the locomotive door transoms are complete and numbered. We passed two inspections in the last week and continue to slowly make progress. Among the next several projects are flashing, shingles, enclosed soffits with vents, entry steps and a handrail. Windows, doors, siding, trim paint and another entry platform will follow those projects.

Engine House

The Roof is Nearly Complete



Engine House

View of All 3 Stalls





          The building is tall enough now that it is visible from the street out front and from a couple of lots away. Neighbors are stopping by to see what it looks like up close after enduring all my construction noise for the past year. They seem to think it looks pretty cool and will be a great place to hang out when the wives are looking for them…

Engine House

Front View of the Engine House Under Construction



Engine House

View From Across the Transfer Table






10/21/07

          Since our last update we attended the Grand Scales convention in Missouri, visited the Wabash, Frisco and Pacific Railroad, engineered at the Flagstaff & Middle Verde's fall meet and visited several California railroads. The California trip included the RS&T Railroad, the Hillcrest and Wahtoke Railroad and Griffith Park railroads past and present. The Griffith Park odyssey included the Panella Pacific Railroad which has the original Griffith Park equipment, the Griffith Park and Southern Railroad, Griffith Park's LA Live Steamers and "Depot Days" at Griffith Park's Travel Town.

          We've posted photos and brief descriptions of several of those railroads here: Recent Updates

          At the A&P RR progress continues on our engine house project. We've completed all 4 walls to the 8' level, received our green tag for the Zonolite insulation and grout on the second lift. We completed that, installed the anchor bolts and extended both ends of the building up an additional 4+ feet for the roof. The trusses and roofing lumber are now on site and the roof construction will begin soon.

8 foot walls

8 foot walls and completed ends



Trusses

The trusses await installation



Lumber

The lumber for the roof has arrived on site






9/10/07

          We had our inspection on our first lift and received our green tag to proceed with grout and Zonolite insulation on the first four feet of our walls. We completed those tasks and have finished three of the four walls to the eight foot level. We still have a few hours more work on the front wall around the three train doors to get that wall completed to the eight foot level. Then we have another pre-grout inspection before we can grout, insulate, place our anchor bolts and add the final four feet of block to the east and west ends of the building. I am so ready to be done with block and concrete work for a while and be able to clean everything up…

8 foot walls

3 of the 4 walls are now 8 feet high





          We have several railroad signs we will be adding in the months ahead. We recently installed one near the pedestrian walkway which will access the loading platform.

Stop Look and Listen

Stop Look and Listen sign near the pedestrian walkway





          We have had several people ask us why we have gone to so much extra work and expense to raise our roadbed, elevate our turntable and transfer table and build lengthy trestles when we live in the desert. Well I am lucky enough to live in an area that has “grandfathered” water rights with irrigation. Every 14 days in the Summer and 28 days the balance of the year, my property is flooded with 12 inches of water from one of our Arizona reservoirs. The average annual rainfall in the Phoenix area is only 8.4 inches so having 12 inches of water every two weeks in the hot summer is of great benefit to the grass, plants and trees on the property. It just makes building and operating a railroad a little more work, but well worth the extra effort. Here are a couple of photos of the water starting to fill the back yard.

Irrigation

Pedestrian bridge and rock creek trestle during irrigation





Rock Creek

Rock Creek trestle and enginehouse viewed from the pedestrian bridge during irrigation






8/20/07

          Our door frames and blocks arrived two weeks ago and we started on our first four foot lift not long after the materials arrived. We have three of the sides completed to the maximum height prior to our next inspection. With some luck this week, we will get the front wall finished to the same height working a couple of evenings after work. We are still hoping to get an inspection this week that will allow us to start on the second lift (next four feet vertically) the weekend of August 25. It is finally starting to look like a building…

4 foot walls

3 of the walls have been constructed 4 foot high





4 foot walls

Northeast corner of the building with rock creek in the foreground




8/04/07

          There's been quite a bit of progress on the A&P RR since our last website update. The summer monsoons are here and the temperature has dropped to just over 100°F. The humidity has risen from 7% to 60% so it's a bit muggy but it's no longer 140°F in the gravel. I didn't have a thermometer that went above 120°F until the peak summer heat had already been broken so this is the best picture I could get... until next summer.

132°F in the gravel

132°F in the gravel. Cooked ham anybody?





          We completed tying and welding rail, rebar, I-beams and angle iron the weekend of the 21st and were ready to have the concrete floor poured the following week.

Rail welded to I-beams

The rails were welded to I-beams to keep them from moving during the concrete pour





          After a few final adjustments, we poured just over 16 yards of concrete on the 27th. Two cement trucks, a pumper and a few hundred feet of hose were needed for the pouring of the floor

Cement truck and pumper

The first cement truck and pumper arrive on the scene





Pouring the Floor

Pouring the concrete floor of the engine house





Concrete Floor

Concrete floor of the engine house viewed from the transfer table



Reverse View

Reverse view of the engine house's freshly poured concrete floor





          We are waiting on delivery of our door frames and blocks, but hope to have both wall lifts and those two inspections completed by the end of August. We also hope to have the roof trusses on site before we head to the Miniature Railroad Convention in Steelville, MO September 14-16.



          Prior to pouring the concrete floor for the engine house we installed sod beneath the transfer table. The BOB-sod we planted thrives when the temperatures at night are in the mid 80's. In just 2 weeks it's difficult to tell the grass hasn't been there all along.

Transfer Table Sod

BOB-sod thriving beneath the transfer table










7/09/07

          Despite the intense Arizona summer heat, we're continuing to make progress on the various projects taking place on the Arizona and Pacific Railroad.

116°F in the shade

116°F in the shade of the patio. The temperature of the gravel we're working in is ~140°F





          Since our last update, gravel and sand has been poured into the floor of the engine house and vibrated multiple times. Three sections of rail have been roughed into place, set at the correct elevation, gauged and welded. Angle iron has been welded beside the rail to ensure a 1" gap for the wheel flanges between the rail and the concrete floor of the building. A rebar lattice work is being constructed to ensure the rail can't move during the pouring of the concrete floor.

Track being prepared for concrete

Track being prepared for the pouring of the concrete floor





Engine House Floor

View of all 3 tracks in the engine house floor





          In addition to the work on the floor of the engine house, the sod has been laid and the re-landscaping project behind the superintendent's house is complete.

Sod has been installed

Freshly installed sod behind the superintendent's house




6/09/07

          As we mentioned last week we've made good progress on the walkway across the two sets of tracks on trestle #5. The block steps at the southern end are complete, the wooden planks have been installed, the handrail has been welded in place, it's primed and ready for final painting.

Walkway and transfer table

Walkway across trestle #5 at west end of transfer table





Walkway across trestle #5

Walkway across both tracks



          In the upper right corner of the picture above you can see in where the re-landscaping project to accomodate irrigation and get dirt is taking place. Bags of topsoil are stacked to be spread, leveled and rolled prior to the installation of sod. In the picture below the locking mechanism on the west end of the transfer table has been installed and awaits paint.



Transfer Table Locking Mechanism

Transfer Table Locking Mechanism







          The soldier course of blocks is complete on both sides of rock creek. The steel fabrication for the new trestle is completed but still needs paint. The holes for bolting the ties to the steel have been drilled and tapped and a few ties were attached to make sure the trestle was at the correct height when the pilons were sunk in concrete and buried in gravel. The north end of the creek where the irrigation valve is, has been cemented and river rocks were sunk in the concrete beneath the trestle.

Rock Creek

Rock creek and the start of old wooden trestle #1's steel replacement





Rock Creek Irrigation Water

Reverse view of rock creek with a little water at the bottom




5/28/07

          Lots of progress since our last update but unfortunately we won't have new pictures until next weekend. Dave's business trip had him out of the country the past few weekends and he hasn't had a chance to take photos of the Arizona & Pacific's progress.

          The rail has been installed on the transfer table and the first of two locking mechanisms has been fabricated and attached to the west end of the table. The east mechanism will be installed after the engine house has had it's concrete floor poured and it's rail installed.

          The planks have been installed on the walkway that crosses the east end of trestle #5 and the block steps leading up to the walkway have been completed.



Transfer Table

Rail has been installed on the transfer table and some of the walkway planks are in place





          Rock creek is nearly complete. The soldier course has been installed on the retaining walls, the river rocks have been placed and the creek bed has been cemented.

          Old wooden Trestle #1 which spanned rock creek has been demolished to make room for the engine house. A steel replacement trestle has been constructed and now spans the creek a very short distance from where the original trestle stood. A new switch will be installed on this trestle that will provide access to the engine house. This link takes you to a map of the right of way .

          The dirt sub-floor for the engine house has been compacted multiple times and is now ready for gravel. We've built up the ground on the north side of the engine house to span the gap between the engine house and the existing right of way with tons of dirt we got from our newest re-landscaping project.

          We've begun to re-landscape the backyard section nearest the back door of the Superintendent's house. That section of grass has never received irrigation water and it's difficult with just underground sprinklers to keep it as green as you'd like when the summer temperatures regularly hit 115°F. The existing grass was removed and several hundred square feet of ground was lowered about a foot by shovel and wheelbarrow. This lower elevation will allow the new lawn to take advantage of irrigation water during the hot summer months. Trenches were dug and underground sprinklers were installed for times when irrigation isn't available. We'll replace the lawn in a few weeks when sod becomes available. This project also provided much needed dirt for spanning the gap between the north side of the engine house and the existing right of way.

          I realize it's not a photo of the A&P RR progress but I did capture this photo of the elevated train last week when I was in Bangkok Thailand. It'll have to do until I can get over to John's house next weekend...



Bangkok Thailand

View of the elevated train in Bangkok Thailand






4/21/07

          With the rain, irrigation and Easter there haven't been many work days since our last update. We did however mount the ties and the 2x6 planking to the transfer table.

Transfer Table

Ties and 2x6 planking have been added to the transfer table






3/17/07

          We removed 40 feet of retaining walls and added 30 feet in different places. This should be the last time we have to remove and replace major sections of our block retaining walls for track realignment – but we have said that before… The stem walls for our new building are up and came out nice in split face block; we wanted to have a solid cut rock look for the foundation. We received our stem wall green tag and were able to grout the stem and start soil preparation for the slab.

Stem Walls

Grouted stem walls and start of soil prep for engine house slab





          We finished the block and metal work on our walkway platform across trestle No. 5. The handrail awaits completion. We added 6 feet in length to the trestle that is now 81 feet long. We painted our additions to trestle No. 5, the walkway platform, transfer table, roller tracks for the transfer table and our sign frame. We also cut, drilled, filed and fitted the balance of the ties for the transfer table.

          Work continues on the new retaining walls on both sides of Rock Creek trestle. Next up is final assembly of the walkway and transfer table, finishing the handrail and continuing the soil preparation for the pouring of the slab.

Rock Creek Retaining Walls

Retaining walls for rock creek






2/24/07

          We welded our extensions on our transfer table, drilled the balance of the 70 holes, welded the bottoms of all the joints, tapped all 70 holes and primed all the surfaces. We also tracked down some reasonably straight 4x4s and cut them to length, filed the corners and drilled the mounting holes for the first 24 of the 35 ties needed for our transfer table.

          In our free time, we moved fourteen yards of concrete from two trucks out in the street in front of the house the 250 feet around to our construction site in the back corner of the rear yard. In all the excitement, I lost track of the number of wheelbarrow loads we moved, but it was somewhere north of 117… We also poured the footer for retaining walls for our new Rock Creek Trestle and the foundation for the rest of our platform steps – more on these projects in the weeks to come. We had help, but it was a still a very long day for everyone involved!



Transfer table and engine house footer

Primed and tapped end of transfer table and engine house footer





One of more than 117 wheelbarrow loads

One of more than 117 wheelbarrow loads is poured








2/10/07

          The concrete and block pillars for the transfer table are complete. They support the 4x4 beam and guide rail that the transfer table's wheels ride on. The 4x4 steel beams of the table have been welded together, the wheels are installed and the structure rolls nicely on it's base. Last weekend we drilled the first 64 holes for mounting the ties to the table. The next step is to tap threads into all those holes and get some primer on the steel.

          The footer trenches for the 3 stall engine house have been dug and the rebar has been bent and tied up. The first city inspection took place this week and the project was green tagged. The next step is to pour the concrete footer.



Transfer table and engine house

View of the transfer table and the engine house





Transfer table

Transfer table under construction





Footer trench

Breaking ground on the engine house's footer trenches








February 2007

          There are always projects taking place on the Arizona and Pacific Railroad. Two of the current projects are the transfer table and the 3 stall engine house. A 21 foot long transfer table is being built to connect a 3 stall engine house to a 80 foot long trestle. The transfer table is designed to appear very much like the A&P RR's trestles with concrete and block pillars which support 4x4 steel beams with railroad ties and rail bolted to the table. After numerous delays, much frustration and many revisions, we finally received city approval on our architect’s drawings for our first three stall engine house and we've broken ground. The building will be 23 feet 4 inches wide and 40 feet long. This page of the A&P RR website is dedicated to following the progress on these projects...









Back to The A&P RR Home Page